News

Milton Road update: September 2024

Published 01 October 2024

Share this page Bookmark this page

The Milton Road project aims to improve public transport, cycling and walking infrastructure to make these sustainable travel options a more attractive alternative to the car.

The scheme is almost complete, with most works due to be finished this month, with only a few small sections being picked up in October. This means next month’s update will form the last of our regular monthly updates on the scheme.  

Overnight works

Our nighttime surfacing works.

We’d like to thank everyone for their patience as we have been carrying out the latest overnight works.

We’ll shortly complete the last of our carriageway surfacing which means all of Milton Road and the associated side roads on the project will have been surfaced. This means that pedestrians and cyclists can cross safely at junctions using smooth and even paths.

Please note the poor weather conditions have affected our ability to proceed with the planned night works as surfacing cannot be carried out in heavy rain. We are continuing to review the situation and will carry out what works we can weather permitting. Please be advised works will now continue on further into this week than originally planned as a result of this delay.  

King’s Hedges junction

King’s Hedges: soft verge area (left) and landscaping works.

This month, the King’s Hedges junction became fully operational as we switched the traffic lights on. 

Since the junction was commissioned on Thursday 5 September, some additional arrows have been painted on both the northbound and southbound approaches on Milton Road. Tarmac has now been laid on the small section of footway outside the Golden Hind pub too. 

All four quadrants on the junction are now fully open and the landscaping is finished. The addition of these trees and wildflowers is brightening up the area beautifully as we approach early autumn. 

We’ll need to revisit this area to take a look at a few areas that need some final adjustments before completing works.

King's Hedges junction opening event

Our King’s Hedges junction opening event.

This month, we also held an event to formally mark the opening of the junction.

Alongside local councillors and stakeholders, we cut a ribbon to celebrate this significant milestone. We’d like to thank councillors and residents for their input and support since the project started. 

Lovell Road crossing

Lovell Road.

Lovell Road’s permanent traffic lights have now been switched on and are operational.

New features on the road

Now that the majority of works on the project have been delivered, you may be seeing and using new facilities on Milton Road.

We thought it might be useful to highlight how these additions to various areas of the road can benefit you.  

Copenhagen crossings

Lovell Road’s Copenhagen crossing is one of 14 along Milton Road.

These crossings are continuous paths, so pedestrians and cyclists have priority at these crossings when they’re travelling along Milton Road.

As they give users priority, they provide an uninterrupted route for quicker, easier and safer journeys. 

Copenhagen crossings also act as a sign to motorists that they’re entering a major or minor road, encouraging drivers to be aware of different surroundings. This ensures a safer experience for residents of Milton Road, neighbouring streets and all users who choose to walk, cycle, wheel or scooter around.

In addition, they help to remind everyone of the recent changes to the Highway Code, that pedestrians and cyclists, where appropriate, have priority when crossing side road junctions. 

Number of Copenhagen crossings on Milton Road: 14 
Locations: At almost every junction on the road.

Continuous segregated cycleways and footpaths

Walking and cycling paths September monthly update

With a line dividing a walkway for pedestrians and a separate path for bicycle riders, these segregated lanes make sure that anyone walking into town to see friends, carrying shopping back to their home, or going for a stroll on a sunny day with relatives can feel comfortable and safe. 

Equally, cyclists commuting to work, children learning how to ride a bike, and those choosing to travel around for health and environmental benefits can feel reassured with journeys on smooth, even ground, away from motorised traffic. 

Cyclists can travel safely knowing that when they use a designated cyclist crossing, they don’t need to push the button for the traffic signals to know they’re waiting. Sensors underneath the crossing can detect when a cyclist is there, so staying safe is easier for cyclists using the road. 

Locations: All along both sides of Milton Road, meaning you can get from the science park to Mitcham’s Corner with dedicated cycle facilities.

Rain gardens

King’s Hedges landscaping and rain garden.

At the corners of some junctions, there are wildflowers and trees planted in what’s called a rain garden.

These are designed to manage runoff rainwater from hard surfaces, so the excess water doesn’t gather or collect on the road. The water then drains downwards naturally, and into the rain garden’s drain at its centre, whilst watering all the plants and helping them to thrive.

Number on Milton Road: 4
Locations: Both sides of Woodhead junction, King’s Hedges junction (at both the north east and south west quadrants).

Improved roundabout

The roundabout has seen a huge improvement since 2022. Top image: Google Earth 2022.

We’ve added new flowers and different types of trees to the roundabout.

Aside from brightening up the area as an attractive place to live, walk, cycle or drive it also enhances biodiversity and helps support vegetation growth. 

The roundabout itself and the surrounding layout has also changed slightly to accompany different users of Milton Road to ensure everyone can move freely and securely in buses, cars, on bicycles, wheels or on foot. The new layout features dedicated crossing facilities for those walking and cycling, ensuring people can safely cross the road, even during the busiest times.

These features will mean parents, children and commuters can have the confidence to cycle along Milton Road, whether they are heading to the shops, school or work. 

Location: Highworth Avenue / Elizabeth Way 

First image: Google Earth 2022.

CYCLOPS junction

King’s Hedges junction.

For cyclists and pedestrians, the dedicated foot and cycle paths don’t stop at a four-quadrant junction.

A CYCLOPS junction – which stands for cycle optimised protected signals – allows for cyclists and pedestrians to cross at the same time, whilst being separated from cars. You can cross with confidence when the green man or green bicycle lights up.

If you’d like to learn more about using a CYCLOPS junction, we’ve created an informative video

Location: King’s Hedges  

Copenhagen crossings

Our final, Copenhagen crossing at Woodhead Drive is very nearly ready for use, marking the last of our 14 crossings to be delivered. 

Woodhead Drive

Works continue at Woodhead Drive.

This month, Woodhead Drive saw huge improvements. 

The kerbing has been installed, the block paving has been laid and carriageway surfacing will shortly take place. 

The rain garden, as well as works to the drains and streetlights, will be completed this week.  

Finally, we’re constructing and surfacing the footway on the south side of the junction and expect this to be finished in the first week of October.

As this is where our construction compound is based, this area will be one of the last sections to be finished, and there will be a handful of works left to finalise after resurfacing the area.

Fraser Road to the Milton Arms - east

We’ve made good progress in this area.

All works have now been finalised, and this section is now open for use.  

Elizabeth Way / Highworth Avenue roundabout

The roundabout traffic lights will shortly be switched on.

We expect the lights to be in full operation in October. 

Ascham Road to Hurst Park Avenue

The small stretch of footway and cycleway between St Lawrence’s Church and Hurst Park Avenue has been surfaced with tarmac, with both red and black resin now installed.

This marks the last section of footway and cycle way to be completed on the west.

General updates

Notice following reports of impersonations 
We’ve received reports of people impersonating Milton Road contractors, pressurising residents into buying unused construction materials. Please be aware our contractors would never do this. 

Highworth Avenue 
Finishing touches to Highworth Avenue are taking place. Planters will be installed shortly, and bollards, signs and final asphalt works to the area have been delivered. 

Seasonal pruning and hedge maintenance 
Now that we’re in September and autumn is already here, we’d like to remind residents that this is an ideal time of year to trim your hedges and hedgerows.

Early autumn is a good time to prune and trim green areas to encourage plants to grow and sprout new leaves, as well as ensuring they’re looking neat within your property boundaries, providing clear visibility for users of Milton Road. 

We’ll also be out and about pruning hedges along Milton Road to ensure they can stay within the highway boundary line and the edging of the paths, so everyone has clear lines of sight and are able to easily use the paths within the space provided.  

Bus stop update

‘Bus stop suspended’ signage will always be displayed with a notice of the new temporary location. Information boards and service provider websites will also display information.

Milton Road bus stops

Bus stop

Status

Westbrook Centre northbound, outside Cambridge Manor Care Home

Open and ready for use

Westbrook Centre southbound, outside shops

Open and ready for use

Union Lane northbound, outside shops

Open and ready for use

Union Lane southbound, outside No.194

Open and ready for use

Downham’s Lane northbound, outside No. 209

Open and ready for use

Downham’s Lane southbound, outside No. 234

Temporary location outside No. 234

Kendal Way northbound, outside No. 319

Open and ready for use

Kendal Way southbound, outside No. 374

Open and ready for use

Golden Hind southbound, outside No. 434

Open and ready for use

Ascham Road northbound, outside No. 97

Open and ready for use

Ascham Road southbound, outside No. 94

Temporarily outside No. 94. 

Fraser Road northbound, outside No. 239

Open and ready for use

Fraser Road southbound, outside No. 318

Open and ready for use

The following bus services are currently stopping on Milton Road: 

Milton P&R (PR5)
Stopping at P&R, Science Park, Kendal Way, Fraser Rd (southbound outside 318 Milton Road and northbound outside 239 Milton Road), Downham’s Lane (southbound temporarily outside 234 Milton Rd and northbound outside 209 Milton Road), Union Lane (southbound outside 194 Milton Road and northbound outside shops), Ascham Rd (southbound temporarily outside 94 Milton Road and northbound outside 97 Milton Road), Westbrook Centre.

Number 9
Stopping at Science Park, Kendal Way, Fraser Rd (southbound outside 318 Milton Road and northbound outside 239 Milton Road), Downham’s Lane (southbound temporarily outside 234 Milton Rd and northbound outside 209 Milton Road), Union Lane (southbound outside 194 Milton Road and northbound outside shops), Ascham Rd (southbound temporarily outside 94 Milton Road and northbound outside 97 Milton Road), Westbrook Centre.

B the busway
Stopping at Westbrook Centre.

Number 2
Stopping at P&R, driving test centre, Cambridge North, driving test centre, Chesterton - Milton Rd.

Number 1
Stopping at Westbrook Centre southbound.  

Drop-in session

The final monthly drop-in took place in early September. We’d like to thank everyone who came along to one of these sessions.

They were designed to help inform residents and the wider Milton Road community when the project’s major works were being delivered. These sessions have therefore now concluded.

If you have any queries, you are still welcome to call us on 01223 699906 or email hello@greatercambridge.org.uk.