The Milton Road project aims to improve public transport, cycling and walking infrastructure to make these sustainable travel options a more attractive alternative to the car.
We’ve been making lots of progress as we move towards the final stages of the project with many sections now complete and available for use.
The Elizabeth Way / Highworth Avenue roundabout is now in use
King’s Hedges Cyclops junction
We are making excellent progress on the Cyclops junction at King’s Hedges, with the north-west quadrant mainly complete, bar a few final details.
Final surfacing of the road and lining still need to be completed, after which the new junction will be fully operational towards the end of the summer. As soon as work has been completed on the last quadrant, all four crossing locations will be open for use.
Overnight works
Thank you for your patience and understanding during our overnight resurfacing works.
We’re now looking to undertake overnight works in the following areas:
George Street
To construct one of our final Copenhagen crossings, we are currently working overnight at the junction of George Street and Milton Road. George Street is therefore closed overnight for approximately six weeks from w/c 1 July. Works are in operation between the hours of 8pm to 6am, due to the limited working space available.
The road is reopened every morning, so should residents need to go out between 6am and 8pm, they are able to exit as normal.
While the road is closed, you will not be able to exit via the junction with Milton Road.
Finishing touches near the roundabout/Arbury Rd shops
We will be carrying out overnight works to finalise some areas on the east, between the Elizabeth Way roundabout and the newly installed bus stop opposite the Arbury Road shops. Works include, but are not limited to, tarmacking the footway, adjusting kerbing and finalising driveways.
We will be starting these works w/c 8 July for approximately ten nights. The works will take place between the hours of 8pm – 6am, with some temporary traffic management in place.
During this time, Milton Road will remain open while we carry out these works and access will be maintained.
North of King’s Hedges
Works on the east and west side are progressing well.
On the east side, final surfacing has now been laid. This means that the east side of Milton Road is now complete from Fraser Road to the end of the project.
On the west side, the Lovell Road Copenhagen crossing is now complete, and works up from the King’s Hedges junction are proceeding well.
For final utility diversion works to be completed on the Copenhagen crossing, Lovell Road will be closed from Monday 8 July for approximately three days.
Access to Lovell Road for vehicles will be via the King’s Hedges Road access point. A walkway onto Milton Road from Lovell Road will be maintained for cyclists and pedestrians.
Completed Copenhagen crossings
We are pleased that the majority of our Copenhagen crossings have been completed, with the total now coming to 11.
The installation of these crossings mean quicker and safer journeys across these junctions for pedestrians and cyclists on Milton Road.
Copenhagen crossings to be completed
Only three Copenhagen crossings are left to be completed: George Street (as detailed above), Woodhead Drive, and Hurst Park Avenue.
Woodhead Drive
We have been reorganising the compound at Woodhead Drive to make space for works at the junction. We will be working on the north side of the footway to construct a new pit for trees and complete the footpath construction. We will then switch to the south side of Woodhead Drive to complete the same and we will then start works to construct the Copenhagen crossing.
Hurst Park Avenue
We are making good progress at Hurst Park Avenue and expect the crossing to be complete by mid to late July.
Arbury Road area
The area in front of the shops is now largely finished.
The final installation of some cycle stands, a small amount of surfacing and a few finishing touches are still to be carried out.
Elizabeth Way / Highworth Avenue roundabout
As above, final works to complete the roundabout have now taken place.
The last step will be to turn the traffic lights on once we have removed the temporary lights at Hurst Park Avenue. Once operational, the new signals will provide dedicated crossing facilities for pedestrians and cyclists, creating a safer environment for all users.
Mitchams Corner area
The crossing at Westbrook is now in use.
There are just a few finishing touches to add before this area is complete.
Bus stop update
The new northbound and southbound bus stops at Kendal Way are now in place and can be used.
‘Bus stop suspended’ signage will always be displayed with a notice of the new temporary location. Information boards and service provider websites will also display information.
Bus stop |
Status |
Westbrook Centre northbound, outside Cambridge Manor Care Home |
Open and ready for use |
Westbrook Centre southbound, outside shops |
Open and ready for use |
Union Lane northbound, outside shops |
Open and ready for use |
Union Lane southbound, outside No.194 |
Open and ready for use |
Downham’s Lane northbound, outside No. 209 |
Open and ready for use |
Downham’s Lane southbound |
Temporarily outside No. 234 |
Kendal Way northbound, outside No. 319 |
Open and ready for use |
Kendal Way southbound, outside No. 374 |
Open and ready for use |
Golden Hind southbound, outside No. 434 |
Open and ready for use |
Ascham Road northbound |
Closed whilst we build a new bus stop. Temporary location outside No. 97 |
Ascham Road southbound |
Temporarily outside No. 94 |
Fraser Road northbound, outside No. 239 |
Closed due to lane closure, with temporary location at No. 209 |
Fraser Road southbound |
Temporarily outside No. 234 |
Buses currently stopping on Milton Road
Milton P&R (PR5)
Stopping at P&R, Science Park, Kendal Way, Fraser Rd (southbound temporarily outside 234 Milton Road and northbound temporarily outside 209 Milton Road), Downham’s Lane (southbound temporarily outside 234 Milton Rd and northbound outside 209 Milton Road), Union Lane (southbound outside 194 Milton Road and northbound outside shops), Ascham Rd (southbound temporarily outside 94 Milton Road and northbound temporarily outside 97 Milton Road), Westbrook Centre.
Number 9
Stopping at Science Park, Kendal Way, Fraser Rd (southbound temporarily outside 234 Milton Road and northbound temporarily outside 209 Milton Road), Downham’s Lane (southbound temporarily outside 234 Milton Rd and northbound outside 209 Milton Road), Union Lane (southbound outside 194 Milton Road and northbound outside shops), Ascham Rd (southbound temporarily outside 94 Milton Road and northbound temporarily outside 97 Milton Road), Westbrook Centre.
B the busway
Stopping at Westbrook Centre.
Number 2
Stopping at P&R, driving test centre, Cambridge North, driving test centre, Chesterton - Milton Rd.
Number 1
Stopping at Westbrook Centre southbound.
Drop-in session
The last monthly drop-in session was held on Monday 1 July. This was advertised in last month’s update to ensure sufficient notice was given due to this update coming out a little later than usual.
Our next monthly drop-in session, with staff from Milestone, will be 11am – 12pm on Monday 5 August at Milton Road Library. Please do note that this is a drop-in session, and visitors are encouraged to free up space for those coming in.